EN effort-driven scheduling
LV plānošana ar nemainīgu piepūli
RU планирование с фиксированным объемом работ
DE leistungsgesteuerte Terminplanung
FR prévisions pilotées par l'effort
Definīcija: The default method of scheduling in Project; the duration of a task shortens or lengthens as resources are added or removed from a task, while the amount of effort necessary to complete a task remains unchanged.
Microsoft Terminology 2023. Entry from the Microsoft Language Portal.