EN BCWS; budgeted cost of work scheduled
LV BCWS; plānotā darba izmaksu tāme
RU БСЗР; базовая стоимость запланированных работ
DE SKBA; Soll-Kosten der berechneten Arbeit
FR CBTP; Coût Budgétisé du Travail Prévu
Definīcija: The earned value field that shows how much of the budget should have been spent, in view of the baseline cost of the task, assignment, or resource. BCWS is calculated as the cumulative time-phased baseline costs up to the status date or today's date.
Microsoft Terminology 2023. Entry from the Microsoft Language Portal.